Below are some actual quotes for some of our recently done projects. The range of the labour costs in these proposals, goes from around £12,000.00, to around £65,000.00, and can give you an idea about our range of values. However, for exact values of your project, fell free to contact us for a quote.

Examples of actual quotations

1. Project summary: adding a new rear, one storey extension, and a new side, two storey extensions

The rear extension was built in order to accommodate a new kitchen and a new dining room. The side, two storey extension, accommodate a new bathroom and a study room (ground floor) and a new bedroom and a new bathroom (first floor). Also, the project included remodeling the first floor, in order to extend the front spare bedroom into the new extension and relocate the existing bathroom, fitting a new kitchen and two new bathrooms, fitting solid wood (oak) floor on existing ground floor and general refurbishment – decorating ceilings and woodwork, etc.

AGREED VALUE OF PROJECT: £66035.00 + [email protected]% for labour and the spending for materials, sanitary ware, kitchen furniture, etc., was around £38000.00 (VAT included)

To view this quotation, click here...

2. Project summary: adding a new side, one storey extension and general renovation + remodeling

The main scope of this projects was the remodeling of the existing kitchen into a new bathroom, plus a pantry/utility room and adding a new section of extension, in order to accommodate a new kitchen. Also, the renovation included: fitting new bathroom suite and toilet in existing bathroom and cloakroom; fitting solid wood floor in lounge; re-carpeting; new wallpaper; general refurbishment – decorating ceilings and woodwork, etc.

AGREED VALUE OF PROJECT: £35250.00 + [email protected]% for labour and the spending for materials, sanitary ware, kitchen furniture, etc., was around £26500.00 (VAT included)

To view this quotation, click here...

3. Project summary: general renovation and remodeling

The scope of this project was the full refurbishment of the bathroom, remodeling the kitchen area and fitting new kitchen, extending the socket ring(s) with additional sockets and replacing all electric heaters with new, fitting new floor and general refurbishment – decorating ceilings and woodwork, etc.

AGREED VALUE OF PROJECT: £12744.00 + [email protected]% for labour and the spending for materials, sanitary ware, kitchen furniture, etc., was around £6450.00 (VAT included)

To view this quotation, click here...

4. Project summary: general renovation and remodeling

In this project was included the upgrade of the heating system, by installing a new boiler and new radiators, remodeling of the first floor WC room, in order to accommodate a shower - wet room, new consumer unit, new flooring throughout (tiles in kitchen, dining, bathrooms, and solid wood – oak – in rest of the property) + full refurbishment of the family bathroom and general refurbishment – decorating ceilings and woodwork, etc.

AGREED VALUE OF PROJECT: £26490.00 + [email protected]% for labour and the spending for materials, sanitary ware, etc., was around £8600.00 (VAT included) + the cost of the boiler

To view this quotation, click here...

5. Project summary: comercial project - nursery refurbishment

This project involved the full renovation of nursery, with everything that one can expect in such works, from the nursery reception room, play areas, and sanitary facilities

AGREED VALUE OF PROJECT: £62875.00 + [email protected]% for labour and the spending for materials, sanitary ware, etc., was around £26000.00 (VAT included)

To view this quotation, click here...